Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Carroll County, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
Carroll County has no zoning ordinance. The Board declined countywide zoning on Sept. 8, 2026. It regulates data centers through a stand-alone ordinance adopted 6-0 on Nov. 2, 2026, which replaced an emergency ordinance of Sept. 14, 2026.
Under that ordinance a data center needs the Board to approve its conformance with the comprehensive plan, after a joint meeting of the Planning Commission and the Board. The ordinance applies to a data center above 100,000 square feet, 50 megawatts or 15,000 gallons a day of private water, or one outside an industrial park in the comprehensive plan.
The ordinance presumes that a data center outside an existing industrial park does not conform to the plan, and that presumption can be rebutted. It exempts legacy projects on county or authority-owned park land under a pre-ordinance agreement, if they are on public water. That Board review is a different instrument from a rezoning, special exception or special use permit, so the state site assessment is not triggered.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- NO ZONING; stand-alone data center ordinance requires Board approval of comprehensive-plan conformance after a joint Planning Commission and Board meeting (no rezoning, special exception or SUP)
- Where
- n/a (no zoning districts; county has no general zoning ordinance)
- What the ordinance calls the use
- Data Center (applies above 100,000 sf, 50 MW, or 15,000 gpd private water, or outside an industrial park in the Comprehensive Plan)
- Provision
- Ordinance to Regulate Hyperscale Data Centers, §§ 2-5, 9 (text posted for the 11-2-2026 hearing, file dated 09.09.26 "without emergency provisions"; adopted that night with no amendment moved in the transcript segment 1:08:05 to 1:09:40); County Code (ecode360 CA1276) has no general zoning chapter (chapter titles read; legislation through 02-05-2024); BOS minutes 6-1-2026 record a member: "Currently, Carroll County is one of eight counties in the state of Virginia without a zoning ordinance."
- If the use is not listed
- n/a: no zoning ordinance, so no unlisted-use rule exists. BOS 9-8-2026 voted 5-0 (1 abstain) to decline countywide zoning and request that the Planning Commission terminate its consideration of it
- Adopted
- Permanent ordinance adopted BOS 11-2-2026, 6-0 (motion Moore, second Bryant; meeting transcript); emergency ordinance 9-14-2026, 5-1, superseded
- Changes and status
- County has no zoning (BOS 9-8-2026 declined countywide zoning). Permanent ordinance adopted 11-2-2026, in force on the as-of date. § 3: rebuttable presumption that a data center outside an existing industrial park does not conform to the Comprehensive Plan. § 9 exempts legacy projects on county or authority-owned park land under a pre-ordinance agreement, if on public water. The Board review is real, but it is none of the three instruments, so § 15.2-2209.5 is not engaged
- Route before the change
- No zoning ordinance
- Date of the change
- 2026-11-02 (emergency ordinance 2026-09-14, superseded)
- Still to read
- BOS minutes of 11-2-2026 (not posted on 11-11-2026)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- ecode360: legislation through 02-05-2024; 2026 BOS minutes read through 10-26-2026. Read Nov. 11, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.