Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Arlington County, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
A full-text search of the ordinance (431 of 435 pages carry a text layer) found no data center term in any use table. The zoning administrator decides whether an unlisted use is similar to a listed one. A use found similar to a permitted use is allowed by right, and a use found similar to a special exception use can only be filed as a special exception. A use similar to none is not permitted. "Data processing" appears once in the ordinance, as an example in the Office use category, and business or professional office is permitted in CM, M-1 and M-2.
Because the outcome depends on that interpretation, whether approval would trigger the state site assessment is unresolved. The county's index of zoning administrator determinations has none on data centers, and its 2025 and 2026 amendment lists and zoning studies carry no data center item. Property-specific determination letters were not searched. The register reads the ordinance effective Oct. 17, 2026 and rates this entry medium confidence.
- State site assessment
- Unresolved. It turns on a pending action or a determination not yet issued.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- ZONING ADMINISTRATOR SIMILAR USE INTERPRETATION (ACZO §12.2.2); no use table names a data center
- Where
- None by name. Full-text search of the ACZO (431 of 435 pages have a text layer) found no data center term in any use table: Art. 4 P districts, Art. 5 R, Art. 6 RA, Art. 7 C, Art. 8 M (CM, M-1, M-2), Art. 11. M table rows for the Office, Utilities, Industrial and Telecommunications blocks read: the business or professional office row is P in CM, M-1 and M-2; 'All other light industrial service uses' P; 'All other warehouse and freight movement uses' and 'All other heavy industrial uses' print no letter. Art. 7 table did not extract cleanly (rows not assigned to columns). Arts. 9 and 10 not read
- What the ordinance calls the use
- (none); 'data processing' appears once, as an example in the Office use category
- Provision
- ACZO 'Effective October 17, 2026': §12.2.2 Similar use interpretations (pp. 221 to 222); §8.1 M use table rules (p.153); Office category §12.2.5.C (p.229); §15.4 Use Permits; §15.5 Site Plans (pp. 380 to 381)
- If the use is not listed
- ADMIN SIMILAR USE INTERPRETATION (§12.2.2): the zoning administrator 'shall be authorized to make a similar use interpretation'; if not similar to any permitted use, 'shall find that the use is not permitted'; if similar to a special exception use, only a special exception application may be filed. §8.1: 'Uses not listed may be allowed pursuant to the similar use determination procedure of §12.2.2'
- Adopted
- n/a: no data center provision in the text layer of the ACZO effective 10-17-2026 (431 of 435 pages). Last amendment on the county list: ZOA-2026-04, adopted 10-17-2026 (telecommunications temporary structures, delinquent taxes, civil penalties)
- Changes and status
- No data center term in the ACZO text layer (pp. 81, 219, 350 and 400 have no text layer and were not read). County amendment lists for 2025 and 2026 (ZOA-2025-01, ZOA-2025-02, ZOA-2026-01 to ZOA-2026-04) and the Zoning Studies page (seven studies, read 11-14-2026) carry no data center item. Zoning Administrator determinations index (ten determinations, seven advice items, 1976 to 2017) has none on data centers; property-specific determination letters not searched. County Board portal searches for "data center" and "data centers", 1-1-2025 to 11-14-2026: no zoning item by title (two matched documents opened, both incidental; the rest judged by title); Planning Commission records not searched. Approvals as the ACZO names them: 'P' uses are by-right and 'may be approved administratively'; a 'U' use needs a use permit, approved by the County Board (§15.4); an 'S' use needs site plan approval, 'a special exception use', heard by the Planning Commission and the County Board (§15.5). No size or megawatt threshold exists because no data center provision exists in the text searched. Whether any existing Arlington facility has been classified was not researched
- Still to read
- property-specific zoning administrator determination letters (not searched)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- County PDF 'aczo_effective_10.17.2026.pdf', cover: 'Effective October 17 , 2026'; county amendment list through ZOA-2026-04, adopted October 17, 2026. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.